We have made a lot of progress! Stairs are done, gutters on, electrical and plumbing inspection passed, most of trim complete. Doors are in. Shower glass installed. We have a few things left but we are close!
Sunday, November 22, 2015
Tuesday, November 10, 2015
Stair progress and railing issue
Beginning of stairs look great. He started on the upper stairs and the railing is too close so he has to take apart the railing to install the rest of the stairs. Then our contractor will now have to fix the railing. Two steps forward one step back
Monday, November 9, 2015
Thursday, November 5, 2015
Sunday, November 1, 2015
Last of wall paint and closets
RJ finished the last of the wall paint. Woo hoo! We are so tired of painting. The floors are finished. And I put together the closets all weekend. They are not done yet but lots of progress.
Electrical starts tomorrow.